Renovations at Elementary School

Renovations at Elementary School
This summer’s elementary school construction projects began just after school dismissed in early June. Our district’s staff and contractors are working diligently together to renovate and reconstruct the inside and outside of our school. Progress has been steady, with weekly job meetings to coordinate work that is currently on schedule for the completion deadline. Classroom cleaning is coordinated as ceiling replacement and/or roofing work in that area is completed. The front driveway and sidewalks have been removed and the site drainage and new driveway layout are being installed. Since this is a hard hat area, no one is permitted on the school property, including the playgrounds or ball fields. We appreciate the patience of those within our community while this project is underway. Please keep in mind that the end result will provide increased safety for all and the school will have a new and refreshed appearance!